Location: Wangaratta VIC
Timeframe: Completion by August 2024
Overview
We’re upgrading Wangaratta’s electricity network to connect the future CleanPeak Energy Wangaratta Solar Farm.
This work will start on 18 March 2024 and be completed by August 2024 (subject to weather and permits).
For more information about the solar farm, visit the Clean Peak Energy website.
What does this project involve?
Our trusted delivery partner Ventia will carry out these upgrades which will include:
- replacing approximately 20 power poles between the Wangaratta Zone Substation and the planned Wangaratta Solar Farm site
- extending the 66kV line from the intersection of Bowser Road and Detour Road to the new solar farm
- installing overhead and underground communications cables along the entire length of the line from the Wangaratta Zone Substation to the solar farm.
This work will allow the new Wangaratta Solar Farm to feed the energy it generates back into the electricity network.
What this means for you
Your power supply may be interrupted one or two times during this project. We will notify you in advance of any planned outages.
There will be traffic management in the area during the project period, to protect the safety of our crews and the community while we’re working. We will let you know in advance of any road closures and detours.
Works notification - 15 to 19 July
From Monday 15 July to Friday 19 July, we will be installing underground telecommunications cables along Ovens Street and Ryley Street in Wangaratta.
This work will happen overnight between 7pm and 6am by our trusted delivery partner, Astelec Group, who will be:
- excavating by open trenching and horizontal drilling
- installing conduits
- installing and laying cables
- reinstating impacted areas.
The locations and expected timing of this work are:
Ryley Street (near Greta Road intersection) - Monday 15 July
Ovens Street (near Woolworths and King George V Gardens) - Tuesday 16 July to Friday 19 July
There will be some noise from machinery and an increase in construction crews, vehicles and equipment during the nightworks. We’ll aim to minimise disruptions and have adequate signage for any detours and alternative pedestrian pathways.
Traffic management will be in place to safely guide vehicles and pedestrians through the work areas.
Please factor in extra travel time during this works period and take extra care when traveling through these areas.
More information and contact
We’ll continue to post updates on this page as the project progresses. You can also follow us on Facebook for more updates.
If you have any questions or concerns regarding the upgrades: